Greater Cairo Metro Line 2
- Collection of the available data from the concerned authorities was followed by magnetic detection field works. Manual detection in some parts was carried out to verify the existing utilities and the new route foreseen to be occupied by the diverted ones.
- Structural design studies for 10 underground stations, annexed structures, cut and cover tunnel, shield-bored tunnel and the viaduct part have been carried out using the most advanced structural analysis methods.
- The structural design also includes the box section under Ismailia Canal with the coffer dam method.
- The water tightness systems have been designed to suit the different elements of the project.
- Examination of interfaces between the new Metro line and other transportation modes to ensure full coordination.