West Cairo Power Station
ACE played a role in developing a 2 x 300 MW power plant which serves the electric network of Cairo, Egypt. The civil works contract consisted of two chimneys of 150 m height each, two boiler houses, two turbine houses, water culverts, water intakes, administration building, GIS building and a workshop. Works encompassed
- Setting out a computerized Management Information System (MIS) to serve the
- Define, operate and monitor the project control system that covers the time, cost and document controls