Egyptian Cement Company: Production Lines I, II, III, & IV

The cement plant, located on the Qattamia-Suez Road in Egypt, has four cement production lines. The production capacity of each line is about 1.365 million tons per year (4,300 tons per day). The project also comprises some auxiliary buildings and service buildings for the engineers and other employees, such as a recreation centre (including a restaurant, gymnasium, etc.), as well as the infrastructure for the plant. The value of the civil works was about 300 million Egyptian pounds for all the four production lines.

The project started in 1996 and was fully operational by the end of 2001.
 
 1    2    3    4